Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Deleting activities on a baselined plan

5 replies [Last post]
Emma Lang
User offline. Last seen 3 years 15 weeks ago. Offline
Joined: 9 Aug 2016
Posts: 45
Groups: None

Hi, I'm looking for some advice on deleting activities on a plan. I need to delete some activities which are no longer valid and redistribute hours to new activities. The plan has been baselined. What is the best way for me to do this? I'm looking for the best practice.

I've tried deleting activities from both the plan and the baseline before and also dissolving activities. If I'm creating new activities I also need to add these into the baseline? I'd like to know the right way to do this, any ideas or advice would be great.

Thanks 

 

Replies

Rafael Davila
User offline. Last seen 12 weeks 4 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

https://www.rationalplan.com/projectmanagementblog/managing-projects-using-project-baselines/

  • However, it is sometimes inevitable to adjust it due to a new requirement that implies a major change to scope or cost. Also in rare cases the project was not well scheduled since the initial phase. In these cases the best solution is to keep the initial baseline and to save the adjusted schedule as a new baseline. 

Frequently unforeseen events can be the cause of substantial re-alignment of the schedule.  Unforeseen events can be a hurricane or other weather event, change orders, Plans and/or Specifications Errors and Omissions, Owner Directed Change of Scope  (additions/deletions), Constructive Change, Consequential Change, Differing Site Conditions, and Jobsite Discovery of Hazardous Materials, to name a few, none of these due to poor planning by the contractor.  By the same token in these cases the best solution is to keep the initial baseline and to save the adjusted schedule as a new baseline. 

Zoltan Palffy
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

make the duration 0 days on those zero from zero is zero 

so you would rather say they were never part of the scope ? I would keep them and also in the activity description add the words (SCOPE DELTED) for each activity. the BASELINE NEVER GETS TOUCHED

why do you think that when you assign a basline to a project that it is no longer listed in the projects diectory ?

becasue that is done by design you do not alter an approved baseline 

Rafael Davila
User offline. Last seen 12 weeks 4 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Keeping deleted activities is not best practice.  Dissolving activities is a shortcut that might induce errors if you do not verify logic.  A few years ago we had a job where one of the buildings was re-designed due to unforeseen conditions.  Footings, structure, architecture, electrical and everything else changed. 

GAO-Schedule-Assesment-Guide-about-activity-deletionjpg-Page1  GAO-Schedule-Assesment-Guide-about-activity-deletionjpg-Page2

For new Baseline best approach is to make updated version your new baseline.

http://www.planningplanet.com/blog/baseline-change-management


 

Emma Lang
User offline. Last seen 3 years 15 weeks ago. Offline
Joined: 9 Aug 2016
Posts: 45
Groups: None

But if I zero out the hours on the current plan and put an actual start and finish date that will claim progress against the baseline plan for activities that weren't carried out? making it appear than progress has been made when it hasn't. Is that correct?

Zoltan Palffy
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

I would leave them in the baseline thats teh whole point of having a baseline. If they have been deleted via a change notice you can put and actual start and finish date on those activites on the date that you were notified that they should be deleted. 

You can zero out the hours and reassigne the hours or you can add a deductive change