Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Printing Gantt Chart

1 reply [Last post]
Ron Beechey
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 13 Jun 2002
Posts: 61

In print Preview on the 11X17 layout, I can see the data but no bars.   Am I missing something?  I have made a few adjustments but have not found the fix to have the bars show.  This is fresh out of the box P6.  Only started working with this version on a stand-alone.  

 

Looks like I found the problem and it is printing now with the Gantt chart 

 

Thanks for anyone that was thinking about the problem :>)

Replies