(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

XLSX

2 replies [Last post]
meobeo u
User offline. Last seen 5 years 30 weeks ago. Offline
Joined: 23 Jan 2019
Posts: 2
Groups: None

Hello there!

I am having issues while importing units and durations on P6, using XLSX files. 

When I import floating point values, it ignores the decimal point and import as an integer. For example, importing 12.05 and it writes 1,205 in the database. 

Does anybody have any idea on why does it happen and how to fix it?

I tried the oracle support here in Brazil but the company analysts only search the knowledge base and send default answers and workarounds that generally don't work. 

I am using P6 PRofessional R16.2 Release 16.2.7 (Build #: 23684).

Thank you!!!

Lee!

Replies

Shaohua Chen
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 29 Dec 2017
Posts: 5
Groups: None

Could you check the resource usage ---graph--calcualte average ?

Zoltan Palffy
User offline. Last seen 21 weeks 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

what is your units per day set on your resource ?

a quick fix would be to run a global change 

where budgeted cost is not equal to 0

then budgeted cost  = budgeted cost / 100

or 

where budgeted units is not equal to 0

then budgeted units  = budgeted units / 100