Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Problem converting XER file from P6 v6.0 to P6 v17.2

1 reply [Last post]
Raul Santos
User offline. Last seen 6 years 25 weeks ago. Offline
Joined: 29 Oct 2009
Posts: 44
Groups: None

I'm getting an error message when trying to convert an XER file from an old version of P6 (version 6.0) to one of the latest versions of P6 (version 17.2).  I get the following error message: 

"An application vent has been intercepted. Please note the event code for reference.

Event code: AVAA0-0863-B"

Anyone knows how to solve this problem?

Replies

Zoltan Palffy
User offline. Last seen 23 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you do not need to convert it just import it ALL software is downwardly compatible.