Oracle Primavera - PM6 Member for 9 years 3 months Member for 9 years 3 months Submitted by waheed elbeih on Fri, 2020-09-18 19:04 Permalink Hi Ahmad AbdRabouI faced the Hi Ahmad AbdRabou I faced the same problem and this is due to Splitting Activites and resitribution of the Units between the Splitted activites the Problem also occurs when you change the Baseline buget units compared to the updated budgeted units to overcome this problem go to the EPS and select the project and then go to settings TAB and in the project settings use the project for calculating the Earned Value is the PRIMAY'S BASELINE and hence, no such change shall be when assigning the baseline EPS>>>>ٍSelect Project >>>>ٍSettings>>>>ٍ User's Primay Baseline Regards Waheed ELbeih Member for 9 years 3 months Member for 9 years 3 months Submitted by waheed elbeih on Fri, 2020-09-18 19:04 Permalink Hi Ahmad AbdRabouI faced the Hi Ahmad AbdRabou I faced the same problem and this is due to Splitting Activites and resitribution of the Units between the Splitted activites the Problem also occurs when you change the Baseline buget units compared to the updated budgeted units to overcome this problem go to the EPS and select the project and then go to settings TAB and in the project settings use the project for calculating the Earned Value is the PRIMAY'S BASELINE and hence, no such change shall be when assigning the baseline EPS>>>>ٍSelect Project >>>>ٍSettings>>>>ٍ User's Primay Baseline Regards Waheed ELbeih Member for 10 years 4 months Member for 10 years 5 months Submitted by Ahmad Abdrabou on Tue, 2018-05-15 07:36 Permalink I'll explain the problem in I'll explain the problem in other words, the contractor submitted an update I loaded the udpate and checked for current progress %, it's 37.67% then I loaded the baseline and checked the current progress % again to find that it's changed to 37.75% what is the reason for that. Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2018-05-14 14:29 Permalink a baseline is the planned % a baseline is the planned % and NEVER chnages the current schedule % complete will change based on progress Member for 10 years 4 months Member for 10 years 5 months Submitted by Ahmad Abdrabou on Mon, 2018-05-14 07:16 Permalink Can you Explain more so that Can you Explain more so that I can test it. Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2018-05-10 14:57 Permalink has to be something different has to be something different ins the schedule Member for 10 years 4 months Member for 10 years 5 months Submitted by Ahmad Abdrabou on Thu, 2018-05-10 13:50 Permalink the problem is, one of the the problem is, one of the sites' Performance % Complete Changes after I assign the Baseline, Only one ! for example: Performance % Complete before assinging baseline is 37.67% Performance % Complete after assinging baseline is 37.75% do you know what happened? Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2018-05-09 13:04 Permalink I would expect the I would expect the performance % complete to changed based on what work got done or did not get done. Why would it stay the same that means that you did nothing Log in or register to post comments
Member for 9 years 3 months Member for 9 years 3 months Submitted by waheed elbeih on Fri, 2020-09-18 19:04 Permalink Hi Ahmad AbdRabouI faced the Hi Ahmad AbdRabou I faced the same problem and this is due to Splitting Activites and resitribution of the Units between the Splitted activites the Problem also occurs when you change the Baseline buget units compared to the updated budgeted units to overcome this problem go to the EPS and select the project and then go to settings TAB and in the project settings use the project for calculating the Earned Value is the PRIMAY'S BASELINE and hence, no such change shall be when assigning the baseline EPS>>>>ٍSelect Project >>>>ٍSettings>>>>ٍ User's Primay Baseline Regards Waheed ELbeih
Member for 9 years 3 months Member for 9 years 3 months Submitted by waheed elbeih on Fri, 2020-09-18 19:04 Permalink Hi Ahmad AbdRabouI faced the Hi Ahmad AbdRabou I faced the same problem and this is due to Splitting Activites and resitribution of the Units between the Splitted activites the Problem also occurs when you change the Baseline buget units compared to the updated budgeted units to overcome this problem go to the EPS and select the project and then go to settings TAB and in the project settings use the project for calculating the Earned Value is the PRIMAY'S BASELINE and hence, no such change shall be when assigning the baseline EPS>>>>ٍSelect Project >>>>ٍSettings>>>>ٍ User's Primay Baseline Regards Waheed ELbeih
Member for 10 years 4 months Member for 10 years 5 months Submitted by Ahmad Abdrabou on Tue, 2018-05-15 07:36 Permalink I'll explain the problem in I'll explain the problem in other words, the contractor submitted an update I loaded the udpate and checked for current progress %, it's 37.67% then I loaded the baseline and checked the current progress % again to find that it's changed to 37.75% what is the reason for that.
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2018-05-14 14:29 Permalink a baseline is the planned % a baseline is the planned % and NEVER chnages the current schedule % complete will change based on progress
Member for 10 years 4 months Member for 10 years 5 months Submitted by Ahmad Abdrabou on Mon, 2018-05-14 07:16 Permalink Can you Explain more so that Can you Explain more so that I can test it.
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2018-05-10 14:57 Permalink has to be something different has to be something different ins the schedule
Member for 10 years 4 months Member for 10 years 5 months Submitted by Ahmad Abdrabou on Thu, 2018-05-10 13:50 Permalink the problem is, one of the the problem is, one of the sites' Performance % Complete Changes after I assign the Baseline, Only one ! for example: Performance % Complete before assinging baseline is 37.67% Performance % Complete after assinging baseline is 37.75% do you know what happened?
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2018-05-09 13:04 Permalink I would expect the I would expect the performance % complete to changed based on what work got done or did not get done. Why would it stay the same that means that you did nothing
Member for
9 years 3 monthsHi Ahmad AbdRabouI faced the
Hi Ahmad AbdRabou
I faced the same problem and this is due to Splitting Activites and resitribution of the Units between the Splitted activites
the Problem also occurs when you change the Baseline buget units compared to the updated budgeted units
to overcome this problem go to the EPS and select the project and then go to settings TAB and in the project settings use the
project for calculating the Earned Value is the PRIMAY'S BASELINE and hence, no such change shall be when assigning the
baseline
EPS>>>>ٍSelect Project >>>>ٍSettings>>>>ٍ User's Primay Baseline
Regards
Waheed ELbeih
Member for
9 years 3 monthsHi Ahmad AbdRabouI faced the
Hi Ahmad AbdRabou
I faced the same problem and this is due to Splitting Activites and resitribution of the Units between the Splitted activites
the Problem also occurs when you change the Baseline buget units compared to the updated budgeted units
to overcome this problem go to the EPS and select the project and then go to settings TAB and in the project settings use the
project for calculating the Earned Value is the PRIMAY'S BASELINE and hence, no such change shall be when assigning the
baseline
EPS>>>>ٍSelect Project >>>>ٍSettings>>>>ٍ User's Primay Baseline
Regards
Waheed ELbeih
Member for
10 years 4 monthsI'll explain the problem in
I'll explain the problem in other words,
the contractor submitted an update
I loaded the udpate and checked for current progress %, it's 37.67%
then I loaded the baseline and checked the current progress % again to find that it's changed to 37.75%
what is the reason for that.
Member for
16 years 3 monthsa baseline is the planned %
a baseline is the planned % and NEVER chnages
the current schedule % complete will change based on progress
Member for
10 years 4 monthsCan you Explain more so that
Can you Explain more so that I can test it.
Member for
16 years 3 monthshas to be something different
has to be something different ins the schedule
Member for
10 years 4 monthsthe problem is, one of the
the problem is, one of the sites' Performance % Complete Changes after I assign the Baseline, Only one !
for example:
Performance % Complete before assinging baseline is 37.67%
Performance % Complete after assinging baseline is 37.75%
do you know what happened?
Member for
16 years 3 monthsI would expect the
I would expect the performance % complete to changed based on what work got done or did not get done. Why would it stay the same that means that you did nothing