Predecessors and Successors in same row of report in P6

1 reply [Last post]
Srinivas Kunapareddy
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 23 Apr 2018
Posts: 2
Groups: None

Hello guys,

 

I am creating a new report in Primavera P6 (R 8.2) and the format I'm looking for is as below:

Activity id             Activity name                 Predecessor name                         Successor name

1                            Activity 1                     Predecessor 1                              Successor 1

2                            Activity 2                     Predecessor 1                              Successor 1

                                                                Predecessor 2                              Successor 2

                                                                Predecessor 3                              Successor 3

3                            Activity 3                     Predecessor 1                              Successor 1

                                                                Predecessor 2                              Successor 2

                                                                Predecessor 3                              Successor 3

                                                                Predecessor 4                              Successor 4

 

As you can see, I'd like to list both predecessor and successor in the same row, one beside the other. 

I attempted to achieve this. But, I'm getting all the predecessors first and then successors by inserting different 'data shources' for predecessors and successors.

Any help in achieving this will be greatly appreciated.

 

Regards,

Srinivas

Replies

Rafael Davila
User offline. Last seen 4 days 2 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Hope this link helps. 

https://www.planacademy.com/find-relationship-lag-primavera-p6/

It might not work with your P6 version.  If not maybe the following can be an option for you to get better reports on schedule logic.

http://scheduleanalyzer.com/ll_brochure.htm

Good luck.