Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 Professional R16.2 Resource Unit of Measure Administration

2 replies [Last post]
Armando Moriles
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 16 Jan 2018
Posts: 4
Groups: None

Hi all,

Using P6 Professional R16.2, I can't find the administration functionality to add a new Resource "Unit of Measure".

Thank you in advance for the help/assistance.

 

Cheers,

Arman

Replies

Armando Moriles
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 16 Jan 2018
Posts: 4
Groups: None

Hi David,

Thanks for that, very much appreciated. I did find the Unit of Measure in the EPPM Database under Administer pull down menu, then Enterprise Data. However, it seemed I have no authority to add a new unit of measure. I will just talk to our Administrator.

Many thanks again.

 

Regards,

Arman

David Kelly
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Unit of measure for material resorces is managed in the Web client if you have an EPPM database. If you have a PPM database, then it isin the admin pull down under categories