Baseline % units complete doesn't roll up.

Why is it happening? And how i can rol up percents to WBS level?

ex.png

C
Cecil Malatji 👤 Member for 15 years 4 months

Good day, I am experiencing a similar problem, resources assigned on both schedules, same budgeted units… but baseline units % complete does not roll up. Please assist…

C
Cecil Malatji 👤 Member for 15 years 4 months

Good day, I am experiencing a similar problem, resources assigned on both schedules, same budgeted units… but baseline units % complete does not roll up. Please assist…

C
Cecil Malatji 👤 Member for 15 years 4 months

Good day, I am experiencing a similar problem, resources assigned on both schedules, same budgeted units… but baseline units % complete does not roll up. Please assist…

C
Cecil Malatji 👤 Member for 15 years 4 months

Good day, I am experiencing a similar problem, resources assigned on both schedules, same budgeted units… but baseline units % complete does not roll up. Please assist…

Z
Zoltan Palffy 👤 Member for 17 years

double check you baseline it appears that there are not resources on those activities

Featured Partner

Top Posters

MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts