Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to determine activities without predecessors or successor

3 replies [Last post]
Binh Vu
User offline. Last seen 6 years 31 weeks ago. Offline
Joined: 13 May 2017
Posts: 4
Groups: None

Hello everyone,

Someone can help me, how to issue the report as below.
Thank you so much.

4984
untitled.png

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 13 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

Tom is correct except that you have to first check the box thats says Log to file and give the log file a location to write to then you have to schedule the project then after that you can view the log file 

Binh Vu
User offline. Last seen 6 years 31 weeks ago. Offline
Joined: 13 May 2017
Posts: 4
Groups: None

Thank you so much.

Tom Boyle
User offline. Last seen 2 days 11 hours ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

In P6, F9. View Log.