Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Revised Program in P6

1 reply [Last post]
Ibraheem Akin
User offline. Last seen 7 years 10 weeks ago. Offline
Joined: 14 May 2013
Posts: 2
Groups: None

Hi Everyone.

I'm currently working on a Revised Program from the last update (in P6), and I've already adjusted and Corrected all dates and Relationships and even I've used Global Change to make Planned % Complete and Actual Percentage complete equal, it worked well for Enginerring, Procurement and Even Construction Stages, but 3 activities (2 from Pre-Construction Documentation and 1 key milestones (Contract period)) didn't change, which is affecting Overall % because the 3 actiities are being update using Physical % Complete, and if I change them to duration % complete it is affecting their actuals, which is affecting Overall % also (driving it back).......

 

Please how do I solve this kind of Issue withouth Changing it's % complete type to Duration??????

 

Thanks & Best Rgards.

Replies

Zoltan Palffy
User offline. Last seen 29 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

run a global change

where physical % complete is greater than 0

then duration % complete = physcial % complete

have you copied this schedule and made this your new baseline ?

what is your earned value calculation setting ?

Budgeted values with current dates

At completion values with current dates 

Budgeted values with planned dates