is you started now would get one big dump of cost during this update
you can manually fix this
the work around is to use it from day 1
this is how to edit store period performance
To edit stored actual units or cost for a past period If you have already defined the financial period,Select Edit User preferenceThen select Application - at the bottom under column level- select thefinancial period for which you want to edit the past period performance ofany specific resource assignment-then closeNext go to the Activity modeClick the resource tabRight click on resource detail & customize-add columns from "FinancialPeriod Value"- Press ok-Now in the Details window you can edit the past performance actual there.