Changing default relationship type

6 replies [Last post]
Usama Baig
User offline. Last seen 8 years 46 weeks ago. Offline
Joined: 26 Nov 2015
Posts: 3
Groups: None

Does P6 allow us to change the default activity type from FS to SS, FF, FS when linking multiple activities?

Thanks

Replies

Zoltan Palffy
User offline. Last seen 1 week 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

no why do people always want to do things backwards  ?

vinay kumar
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 29 Oct 2014
Posts: 5
Groups: None

When we want to link several activities of similar type to define a sequence we need to manually link one by one. like FS if we have an option to choose whatever a relation type to be considered as default by the program, we can complete the task simply. In my housing project we have 80 roads with 9 different utilities where we have to give such relations on a go. 

Rafael Davila
User offline. Last seen 19 weeks 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Why not defining link type when performing multiple links as a single step?

You can create a filter to display only selected activities when linking activities on a job with many activities to make it easier.

Maybe you did not looked for the option for performing multiple links as a single step within your software, it is not an uncommon task.

Good luck.

adab azeez
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50

I also tried to find this technique. But i came to the conclusion that their is no such way to get SS as default relationship.

Zoltan Palffy
User offline. Last seen 1 week 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

bigger question is why ?

David Kelly
User offline. Last seen 2 years 48 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

no