My previous actual units changes

A
Ahmed Farag 👤 Member for 9 years 11 months

Hi;

Can anyone help with the following.

My previous actual units changes everytime I update (Schedule Project). I'm Sure I Untick the mark next to "Recalculate Actual Units & Cost when duration % complete changes" at project level.

note:- the actual changes to be linear change (for ex. if actual units are 24 for 4 periods each period changes to be 6 units)