Cost of level of effort activity

3 replies [Last post]
shafak salam
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 23 Apr 2016
Posts: 5
Groups: None

I have a level of effort activity with duration % complete. Cost is assigned to it as material resources price. But the cost is not getting distributed through the duration of the activity. In the profile/spreadsheet, the cost just stays in the start date of the activity. No idea why..

Replies

shafak salam
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 23 Apr 2016
Posts: 5
Groups: None

Thank you..

shafak salam
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 23 Apr 2016
Posts: 5
Groups: None

Thank you..

Zoltan Palffy
User offline. Last seen 16 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to the activity directory then the resource tab right click in the bottom resource window add a column for curve

then assign a curve to the resource