Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost of level of effort activity

3 replies [Last post]
shafak salam
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 23 Apr 2016
Posts: 5
Groups: None

I have a level of effort activity with duration % complete. Cost is assigned to it as material resources price. But the cost is not getting distributed through the duration of the activity. In the profile/spreadsheet, the cost just stays in the start date of the activity. No idea why..

Replies

shafak salam
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 23 Apr 2016
Posts: 5
Groups: None

Thank you..

shafak salam
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 23 Apr 2016
Posts: 5
Groups: None

Thank you..

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to the activity directory then the resource tab right click in the bottom resource window add a column for curve

then assign a curve to the resource