Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2016-03-01 21:08 Permalink run a global change make sure run a global change make sure that where activity status is not equal to comeplete then duraiton % complete = physcial % ciomplete Member for 11 years 6 months Member for 11 years 7 months Submitted by aejaz9176 on Tue, 2016-03-01 14:21 Permalink A-1 type task dependentA-2 A-1 type task dependent A-2 Fixed Duration & Units A-3 Physical % complete A-4 & A-5 i used default setting. [[wysiwyg_imageupload:3621:]][[wysiwyg_imageupload:3622:]] Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2016-03-01 13:19 Permalink Hard to tell can not see the Hard to tell can not see the pics 1. Is the activity type task dependent or resource dependent ? 2. What are you using for duration type ? 3. What are you using for % Complete type ? 4. Under Calcluations do you have Link Actual and actual this period units and costs checked 5. Under Calculations do you have Replace Actual Units and Costs When duration % complete changes ? Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2016-03-01 21:08 Permalink run a global change make sure run a global change make sure that where activity status is not equal to comeplete then duraiton % complete = physcial % ciomplete
Member for 11 years 6 months Member for 11 years 7 months Submitted by aejaz9176 on Tue, 2016-03-01 14:21 Permalink A-1 type task dependentA-2 A-1 type task dependent A-2 Fixed Duration & Units A-3 Physical % complete A-4 & A-5 i used default setting. [[wysiwyg_imageupload:3621:]][[wysiwyg_imageupload:3622:]]
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2016-03-01 13:19 Permalink Hard to tell can not see the Hard to tell can not see the pics 1. Is the activity type task dependent or resource dependent ? 2. What are you using for duration type ? 3. What are you using for % Complete type ? 4. Under Calcluations do you have Link Actual and actual this period units and costs checked 5. Under Calculations do you have Replace Actual Units and Costs When duration % complete changes ?
Member for
16 years 3 monthsrun a global change make sure
run a global change make sure that
where activity status is not equal to comeplete
then duraiton % complete = physcial % ciomplete
Member for
11 years 6 monthsA-1 type task dependentA-2
A-1 type task dependent
A-2 Fixed Duration & Units
A-3 Physical % complete
A-4 & A-5 i used default setting.
[[wysiwyg_imageupload:3621:]][[wysiwyg_imageupload:3622:]]
Member for
16 years 3 monthsHard to tell can not see the
Hard to tell can not see the pics
1. Is the activity type task dependent or resource dependent ?
2. What are you using for duration type ?
3. What are you using for % Complete type ?
4. Under Calcluations do you have Link Actual and actual this period units and costs checked
5. Under Calculations do you have Replace Actual Units and Costs When duration % complete changes ?