unit % Complete ( attachments )

Member for

16 years 3 months

run a global change make sure that 

where activity status is not equal to comeplete 

then duraiton % complete = physcial % ciomplete 

Member for

11 years 6 months

A-1 type task dependent

A-2 Fixed Duration & Units

A-3 Physical % complete

A-4 & A-5 i used default setting.

[[wysiwyg_imageupload:3621:]][[wysiwyg_imageupload:3622:]]

Member for

16 years 3 months

Hard to tell can not see the pics

1. Is the activity type task dependent or resource dependent ?

2. What are you using for duration type ? 

3. What are you using for % Complete type ?

4. Under Calcluations do you have Link Actual and actual this period units and costs checked

5. Under Calculations do you have Replace Actual Units and Costs When duration % complete changes ?