Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

unit % Complete ( attachments )

3 replies [Last post]
AEJAZ AHMED AHMED
User offline. Last seen 7 years 38 weeks ago. Offline
Joined: 6 Apr 2014
Posts: 7
Groups: None

Hi Guys

i want to know about unit % Complete.in my programm Activities window shows 1.68% whereas Resourece assignment  shows 2.23%.whats wrong in my programm?

i attached following pics.

can you explain me details.

Pic-01

Pic-02

Replies

Zoltan Palffy
User offline. Last seen 9 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

run a global change make sure that 

where activity status is not equal to comeplete 

then duraiton % complete = physcial % ciomplete 

AEJAZ AHMED AHMED
User offline. Last seen 7 years 38 weeks ago. Offline
Joined: 6 Apr 2014
Posts: 7
Groups: None

A-1 type task dependent

A-2 Fixed Duration & Units

A-3 Physical % complete

A-4 & A-5 i used default setting.

3621
01.jpg
3622
02.jpg

Zoltan Palffy
User offline. Last seen 9 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Hard to tell can not see the pics

1. Is the activity type task dependent or resource dependent ?

2. What are you using for duration type ? 

3. What are you using for % Complete type ?

4. Under Calcluations do you have Link Actual and actual this period units and costs checked

5. Under Calculations do you have Replace Actual Units and Costs When duration % complete changes ?