Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2016-02-08 13:39 Permalink that is the whole point of a that is the whole point of a schedule to see how activites are planned and progress which lead up to the milestone. EVERY activity has float until it is has an actual finish date. its like saying I have to be at work at 8:00 am but I dont care what time that it is now. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2016-02-08 13:39 Permalink that is the whole point of a that is the whole point of a schedule to see how activites are planned and progress which lead up to the milestone. EVERY activity has float until it is has an actual finish date. its like saying I have to be at work at 8:00 am but I dont care what time that it is now.
Member for
16 years 3 monthsthat is the whole point of a
that is the whole point of a schedule to see how activites are planned and progress which lead up to the milestone.
EVERY activity has float until it is has an actual finish date.
its like saying I have to be at work at 8:00 am but I dont care what time that it is now.