Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity bars not changing colour

3 replies [Last post]
leighton rogers
User offline. Last seen 8 years 34 weeks ago. Offline
Joined: 9 Jan 2016
Posts: 15
Groups: None

Hi Guys,

 

quick one for you experts,

 

i have activities started and certain activities have changed colour with progress ie red to half black with 50% progress but otheres havent with the same progress?

could someone help me with this?

Thankyou.

 

Leighton

Replies

Zoltan Palffy
User offline. Last seen 26 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that the progress bar is checked and that the color is DIFFERENT

 

did you click the default button ?

leighton rogers
User offline. Last seen 8 years 34 weeks ago. Offline
Joined: 9 Jan 2016
Posts: 15
Groups: None

Thanks for your reply.

ive checked all the bar options.  i have blue activities started and some at 30% and the actual work bar isnt showing at all but it is showing on my red critical bars at 50 %

 

 

Zoltan Palffy
User offline. Last seen 26 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

red would mean that the remaining portion of that activity is critical if it is red.

Just to make sure go to bars and on the right select default.