Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Create Multiple Colours on the Same P6 Bar

3 replies [Last post]
Ife Olyke
User offline. Last seen 10 years 28 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147

Hi Folks,

 

I want to put two colours on the same bar. Basically, I want to show where

  • Let’s say you have an activity scheduled (baselined) to start 1st Feb 2014 and finish 28th Feb 2014. Bar colour for the activity is green.
  • By 15th March 2014, activity has not finished and still has up to 30th March to complete

  

I want to show on the same bar as follows;

  • From 1st Feb (Baseline start) to 28th Feb (Baseline finish) bar colour RED
  • From 28th Feb (Baseline finish) to 15th March (Current Data Date) bar colour WHITE
  • From 15th March (Current Data Date) to 30th March (Expected Finish Date) bar colour YELLOW

 

Has anyone done similar thing before? Please share

 

Cheers

olyke

Replies

Ife Olyke
User offline. Last seen 10 years 28 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147

Thanks guys.

Jose Frade
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None

Hello

Best way is to Show two bars for the activity:

1. Baseline - one bar

2.Actual and forecast - another bar

 

Reason: If trying to combine in one bar and where some dates overlap (Ex: Plan st 01/02 and fs 28/02; Actual st 15/02 and pln fs 30/03). The period on mentioned example between 15/02 and 28/02 will be shown only in one of the bars - the one being defined later on the sequence of bar definition window)

 

No problems with collors (you can define as much as you want for different status of the work): baseline, done, forecast, float, etc.

 

Caution: White collor will require special ability when displaying in white background or printing.

 

Regards

JMFrade

Raymund de Laza
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 22 Nov 2009
Posts: 762
Use UDF dates and activity coding.