P6 R8.4 stand-alone

2 replies [Last post]
Alexandre Faulx-B...
User offline. Last seen 3 years 1 week ago. Offline
Joined: 20 Jan 2003
Posts: 1355

Hello PPlanners,

I have recently moved to P6 R8.4 on a stand-alone machine, namely build #11214;

to my surprise, I have noticed that the Maintain Baseline dialog does not show the Update Baseline option; I have gone to the online help, and the Update Baseline is still mentionned;

how will I update a baseline as I was doing when using the previous releases of the software?

will Oracle-Primavera insert this option again in the software?

Thanks for your help,

Alexandre

Replies

Johannes Vandenberg
User offline. Last seen 1 year 11 weeks ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi Alexandre

Yes, you are correct the update baseline has been deleted in P6 8.4.

The option available is to restore the baseline, modify to suit and maintain the new updated  baseline. Then re-assign.

Regards Johannes