WBS summary activity

6 replies [Last post]
moutaz aldeib
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Hi Planners, Is there a difference between WBS summary activity WBS level? I see they are the same?? Best Moutaz

Replies

moutaz aldeib
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Thanks Johannes, so this is the only difference. Is it common used this kind of activity or rare?

Best,

Moutaz

Johannes Vandenberg
User offline. Last seen 1 year 20 weeks ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi Moutaz

The WBS is a roll-up of all the activities under the WBS.

A WBS summary does the same but you can add resources, costs and expenses. 

Regards Johannes

moutaz aldeib
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

hi Zoltan,

My question is that: WBS Summary activity is a kind of an activity type that roll up the activities under a WBS element and WBS level is doing the same, is there any difference?

Best

Zoltan Palffy
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

left hand side click on wbs

Safdar Imam
User offline. Last seen 10 years 16 weeks ago. Offline
Joined: 15 Mar 2015
Posts: 2
Groups: None

How to create wbs?

Zoltan Palffy
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

not sure what the question is here. The WBS summary activity is an ACTIVITY TYPE a wbs level can mean that you roll up your activites to a certain wbs level which has noting to do with wbs summary TYPES of activities.