Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Type = WBS Summary

No replies
Rodney Jones
User offline. Last seen 25 weeks 6 days ago. Offline
Joined: 17 Jun 2012
Posts: 65
Groups: None

Hi All,

 

I just need some clarification,...............Do WBS Summary Activities drive other Activities if used as Predecessor?

 

I think not but would appreciate confirmation.

Cheers,

 

Rod

david kelly
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None
no! WBS summary activities and LoE activities can have no schedule impact, and cannot be levelled
Rodel Marasigan
User offline. Last seen 5 weeks 1 hour ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Rod,

The WBS summary activity functions more like a "hammock" activity, summarizing the activities within the WBS element it represents. While it can be linked to other activities for dependencies, it doesn't directly influence the scheduling or sequencing of those activities, unlike MS Project, where the summary bar can drive activity when linked to a network or used as a predecessor.