Activity Type = WBS Summary

Hi All,

 

I just need some clarification,...............Do WBS Summary Activities drive other Activities if used as Predecessor?

 

I think not but would appreciate confirmation.

Cheers,

 

Rod

D
david kelly 👤 Member for 10 years 5 months

no!

WBS summary activities and LoE activities can have no schedule impact, and cannot be levelled

R
Rodel Marasigan 👤 Member for 19 years 9 months

Hi Rod,

The WBS summary activity functions more like a "hammock" activity, summarizing the activities within the WBS element it represents. While it can be linked to other activities for dependencies, it doesn't directly influence the scheduling or sequencing of those activities, unlike MS Project, where the summary bar can drive activity when linked to a network or used as a predecessor.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts