tracking physical % complete & % cost complete separately in the same project

1 reply [Last post]
müjdat özacar
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 30 May 2009
Posts: 13

Hi all,

When I track my physical progress i follow this way: after i assign resources to primavera(manhours and materials) i define 1$/h unit price for manhour resource so budgeted labor units gets equal to budgeted total cost . anyway when updating as per baseline i can track physical progress perfectly from earned value and performance % complete columns.
But now i wanna track also project cost complete in the same project %(as per Contract BOQ) separately in primavera including labor and material cost .. 
Is there any way to do it?

Thanks in advance

Mujdat Ozacar

Replies

Zoltan Palffy
User offline. Last seen 26 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you already have Budgted total cost and Budgted Units 

for your actual costs you can run a global change where actual costs equals Budgeted cost * % complete

for actaul manhours you can run a global change where actual units equals Budgeted Units * % complete