Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to remove symbols (*, A) from Dates

4 replies [Last post]
nicolò spagna
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 24 Nov 2014
Posts: 4
Groups: None

Hello everyone,

when I creat a report in order to extract the Finish Dates of the Activity IDs and put them in an excel database, activities that are in progress or performed, will be extract in this way:

 PRC-3000/010Completed01-09-14 A15-09-14 A

Activities with constraints, will instead appear in this way:

 PRC-3010/030Not Started10/11/201411-06-15*

 

Is that possible to remove these letters/codes in order to have always the same layout of the data?

This is how I would like they all appear:

 PRC-3000/030Not Started19/11/201407/07/2015
 PRC-3000/040Not Started08/07/201529/08/2015

 

Thanks in advance!

 

Ciao

Nicolò

Replies

Zoltan Palffy
User offline. Last seen 1 week 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

yes Paul has the correct solution use find and replace in excel 

Paul Harris
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

Nicolò

I do not think your can,but you could try User Defined Fields and Global Change to put the dates into the field or try displayinm other date fields such as Actual and Remaing Dates, but displaying these get problematinc as they either display blanks or the wrong dates. For Example the Early and Late Dates do not display Actual Dates correctly.

Regards

Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia
http://www.eh.com.au,  http://www.primavera.com.auand http://eastwoodharris.com.
Project Control Consultants and Planning and scheduling software book and training material publishers
Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/

nicolò spagna
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 24 Nov 2014
Posts: 4
Groups: None

Thanks Paul,

 

for the moment this is very usefull. I didn't know about the ~

But i wanted to know if it was possible to avoid this process, just using some setting in Primavera.

 

Thanks

Nicolò

Paul Harris
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

If you post the report to Excel you can remove the "*" and "A" by using find and replace.

To remove the "*" you must use the find option of "~*" and thne Excel will specifically look just for the "*". If you do not use this option the all data will be removed. Leave the Replace with field blank.

Regards

Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia
http://www.eh.com.auhttp://www.primavera.com.auand http://eastwoodharris.com.
Project Control Consultants and Planning and scheduling software book and training material publishers
Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/