Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

How to remove suffixes from dates and display both dates for milestones in Primavera P6

If you came into Primavera P6 from a Microsoft Project background, you would have noticed that actual dates have the suffix “A” appended to them, and constrained dates also have an asterisk appended. And milestones have a blank date field depending on the type of milestone.

In this YouTube video, I will show you a trick you can use to

  1. Remove the appended “A” from actual dates
  2. Remove the appended asterisk (*) from constrained dates
  3. Display finish dates for Start Milestones
  4. Display start dates for Finish Milestones

Market Place

No results found... (try selecting a different content filter)