How to remove suffixes from dates and display both dates for milestones in Primavera P6
![](http://www.planningplanet.com/sites/default/files/imagecache/wysiwyg_half_page/user/blog/remove_suffixes_cover.png)
If you came into Primavera P6 from a Microsoft Project background, you would have noticed that actual dates have the suffix “A” appended to them, and constrained dates also have an asterisk appended. And milestones have a blank date field depending on the type of milestone.
In this YouTube video, I will show you a trick you can use to
- Remove the appended “A” from actual dates
- Remove the appended asterisk (*) from constrained dates
- Display finish dates for Start Milestones
- Display start dates for Finish Milestones