Unable to assign project code to activities

2 replies [Last post]
Robert McGhee
User offline. Last seen 8 years 32 weeks ago. Offline
Joined: 27 Mar 2008
Posts: 15
Groups: None

Have added a "project" code and when I go to Enterprise/Project Codes it shows up, but cannot find it on the list when I try to assign the code to an activity and have chosen the "Display: All Values."

Replies

Zoltan Palffy
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

what you added are codes at the project level NOT the activity level. To add codes at the activity level go to activities then select Enterprise then select activity codes.

now you can assign the activities to these codes 

Raymund de Laza
User offline. Last seen 5 weeks 20 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762
Robert, Project codes are for projects and activity codes are for activities. Create activity codes to be assigned to an activity.