Increase Resource Limit

1 reply [Last post]
Gatet Prasojo
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 3 Sep 2013
Posts: 5

Hi, can anyone help me.

 

I have this project that use several area as the resources.

The area is the shop where the activities are being done.

Now when i display resource usage profile on bottom, 

2095
resources_usage_profile.jpg

 

It will show every resource that i used, and how may manhours are assigned to that resources.

My problem is, the limit is not correctly assigend. 

How do i increase a resources limit?

2096
resources.jpg

Replies

Ravi Katare
User offline. Last seen 10 years 30 weeks ago. Offline
Joined: 14 Jul 2014
Posts: 23
Groups: None

Hi,

Soln:

Go to Resource directory, select concern resource, select units & prices tab & change the Max units/time value.

 

- Ravi