Cost different after import

Hi all,

I have just imported a programme onto my P6 and the total cost is lesser than the one in the programme i imported it from.

Can someone please help? I suspect it's a setting issue but couldnt figure it out.

Regards,

Patrick

R
Ravi Katare 👤 Member for 12 years

Hi

It could be plenty of reasons, try to check some things like

1. check duration before and after, if it differ means you have same calender names

2. check planned dates

3. check resource IDs

4. check price/unit rates

 

- Ravi