Remaining early start

2 replies [Last post]
Jean Desjardins
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Hi everyone,

I have an activity that was completed earlier than planned (nov 1st instead of nov 8)

Meanwhile its successor remaining early start date remains on november 11th. (the data date is nov 1st)

Is there a way to advance the rem. early start to nov. 1st ?

The only way I found to resolve that is removing the link with the predecessor.

Jean

 

Replies

Jean Desjardins
User offline. Last seen 8 years 29 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Thank you Kylee,

In the schedule options I've checked "Progress override" instead of "Retained logic"

Regards

Kylee Foster
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 14 Aug 2007
Posts: 10

Hi Jean,

Is there incomplete logic link on the predecessor task?  This will still push the successor task even if the (first) predecessor is finished.  If you've time better to fix this than just deleting the link and it would change the successor task start date.  Careful with interproject links too if that is applicable.

Regards, Kylee.