Resource Allocation issue

No replies
Kevin John McGovern
User offline. Last seen 1 day 16 hours ago. Offline
Joined: 18 Jul 2007
Posts: 5
Groups: None

Hi, I am using V23.12.

I have a fairly small schedule which is fully resource loaded. All dates etc. are correct folowing update.

However, on one activiy in particular, the resource loading has been spread way beond the activity completion date.

Activity completion date is 23 Sept and the resource loading goes on into November. Curve is linear and late dates are only 2 days beyond finish dates.

Anybody any ideas how to correct this?

Thanks