MS Project Copy Tables and Formulae between Projects

1 reply [Last post]
Philip de Havilla...
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 4 Oct 2011
Posts: 6
Groups: None

Hi Team,

I have created a table to do some analysis that I want to be available to all my projects and eventually available to the whole enterprise.

I have copied the table view into the Global field and it is available in other projects now that is good.

However when opening up this table view in other projects there are a few number fields I have created with formulea in them, there columns do not copy accross correctly and the formulae has gone, I can manually add the formulae back in by copying the field.

But to make it easy for other users is there a way to ensure these fields with formulae copy accross correctly.

Thanks

Phil

Replies

Bogdan Leonte
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 18 Aug 2012
Posts: 285

Hello,

you also have to copy the fields with formulae in the global template and then each user has to transfer it back from the global template.

Best regards,
Bogdan