MS Project 2016 - Renumber wbs of selected task is greyed out in MS project

1 reply [Last post]
Pranab Kumar Deb
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

Hi All, 

 

I am using MS Project 2016 and want to renumber a selection of activities but the renumber wbs selected task in ms project 2016 is greyed out.  I have tried the task sheet view and removing the autofilter, nothing works

 

Please help. 

 

regards

 

Pranab 