Hi Everyone,
I am working in MS Project 2016 professional. My question concerns leveling.
I have a couple of strategic projects that our R&D department is working on in an one planning. In this planning every stratgic project is a summary task, not a subproject. These strategic project may have in some cases have a predecessor/successor connection but in most situations this is not the case.
When I use the leveling option (week to week basis) then Project resolves quite a lot of over allocations but doing so it stretches individual task of a summary task over a very long period of time leading to an huge durartion time of this summary task or project.
This may give the most effective resource usage but for other reasons I do not want one task being scheduled in feb. 2018 and the next one in dec. 2018 and another somewhere 2019.
Is there a way to control this without losing the leveling functionality of Projects.
Many thanks for any advise.
Martin