Finish Date Calculation Questions

1 reply [Last post]
Casey F
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 28 May 2016
Posts: 17

I have a simple activity that has a completed predecessor and the successor is FS.  My data date is 9/1/17 with 1 day remaining on a standard 5 day calendar with no holidays.  Why is project calulating the finish date as 9/7/17, as opposed to 9/4 or 9/5?

Replies

Tom Boyle
User offline. Last seen 11 weeks 5 hours ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Hi Casey,

Unlike the data date in P3/P6, MSP's status date does NOT enter into the schedule calculations.  In addition, there is no Original Duration, and the following always holds true: Duration = Actual Duration + Remaining Duration.

I expect MSP is calculating the finish date of 9/7/17 because that's what it was scheduled for already.

Updating the task status in MSP requires a bit more work than Primavera.  http://ronwinterconsulting.com/MS_Project_for_Construction.pdf

Good luck, tom