Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Newbie Question. Creating dependencies that are not end to start dates

5 replies [Last post]
Timothy Reducha
User offline. Last seen 6 years 40 weeks ago. Offline
Joined: 3 Nov 2015
Posts: 13
Groups: None

Good day all you Planning Professionals! I beseech you for your wisdom. A lowly CM seeks a simple(well,,not for me) answer to a simple question. I am using MS Project 2013. I want to create a dependency from finish to start but i'm not sure how to do it, because the dates aren't exactly end to start necessary.

 

The situation: I am wrapping scaffolding around a builidng i want to work on. And yes,,technically i need the scaffolding up before i can begin, but the reality is that, its a big builidng, and if i start at one end of the building, by the time it's 30% complete, i can have men on the scaffolding working away while the balance installation continues.

 

How do i do this kind of dependency?

This is really important because i now want to insert an additional task inbetween other works, and i'm hoping that with depencency's inseerted, i won't have to manually configure the whole plan. It'll just automatically drop the whole plan down or on, in length/duration, so i won't have to change the whole plan. 

 

Much appreciated!! Thank you. Timothy

Replies

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

There is a limitation in MSP that will prevent you from easy modeling of concurrency because it will not allow two links between activities. A workaround can be to add a milestone in between any of the two links.

I used a 2d lag, but could have been 1.5d to represent 30%, the same calculations you would do to calculate the split. Easy and transparent.

What you should avoid is the use of negative lag, a common workaround used by MSP users as to tackle this limitation.

With Spider Project in addition to time lag we we can model volume lag as a percentage but there is no equivalent for this in MSP. The software will calculate the time required to realize the % volume of work depending on production rates, another parameter lacking in most other software.

MSP-SSFF photo SS-FF-MSP_zps9vzwyamf.png

The following link shall provide you with some insight. Note that I do not agree with the conclusion because it is missing what happens with resource leveling. Anyway it makes no harm to see what others suggest. Some schedulers do not use/understand how software resource leveling works, therefore I am not surprised the article misses how resource leveling might spread apart the activities.

http://www.gbaprojects.com.au/uploads/files/whitepaper_-_poor_planning_n...

Trevor Rabey
User offline. Last seen 2 years 1 day ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None

Stage 1 of scaffolding takes as long as it takes to get enough scaffolding up so that people can work on it.

Break the scaffoldong into stages, and use FS0 links only.

Example: if you had 15 bathrooms and the plumber goes in and does his part first and then the tiler comes in behind him, you don't have to do all of the plumbing before starting the tiling, so you would break it down room by room.

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

This approach might result in longer development schedules, because they incorrectly use sequential logic. Not starting downstream activities until the upstream ones are complete inexorably lengthens the path. Instead, we must use the logic of CONCURRENCY to shorten the paths.

http://www.me.utexas.edu/~jensen/network_02/topic_pages/kanegaronkar/opinions.htm

There are no perfect models as some pretend, while none is perfect they can be good enough and without doubt better than nothing. 

The risks of splitting activities that shall be executed continuously can be far more dangerous than pretending concurrent logic does not exists. This is specially true if your model is to apply resource constraints, it might spread apart the segments of an activity that shall be continuous. In such case use of SS(+lag) in combination to FF(+lag) relationships will make a better model, though never perfect.

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Timothy

You should only use Finish Start links in your programme.

Split your scaffolding task into as many stages as are necessary and use FS links from each stage to the following trade.

SS lead lags distort the logic because when your programme update data line passess the link date then all logic is lost.

Best regards

Mike Testro

Robert Bell
User offline. Last seen 6 years 20 weeks ago. Offline
Joined: 8 Jun 2016
Posts: 49
Groups: None

Hi Tim, you want your logic to reflect reality so if you don't need to wait until all scaffolding is up to begin, then this isn't the link you want. I would use either a SS relationship with a lag, or better yet, create an activity that is SS with the scaffolding that represents that 30% until they can truly begin, and then link the start of that work from that activity instead.