I'm not a big user of MS Project, so excuse my ignorance
We've got a design programme which has been baselined and is used for Earned value Management
We are expecting a lot of CEs (variations) to come our way throughout the life of the project
We want to include these CEs in our Earned value metrics
We don't want to loose historical earned value performance metrics by doing a total re-baseline each time we add a CE
I was hoping to be able to add new tasks representing these CE's to the existing performance baseline, but that doesn't seem to be possible? it seems the only way to get new tasks into a baseline is by either creating a brand new baseline, or completely overwriting an existing one?
Am I missing a trick, or is there no way to increase the BAC of an ongoing project whilst maintaining the historical BCWS S-curve?
Any advice greatly appreciated
Cheers,
G
Replies