Hi all ,
Is there a way , by which we can copy tasks with links in one project to another .
To make it more clear. I have 12 projects in which after one major tasks or you can say mile stone , subsequent tasks are similar in all projects. Problem being these tasks have some lead / lag and also parallel status with mile stone or among themselves. To make it more standard and convincing for client , i want to keep relationships and durations intact in all projects.
But after first project , i have to go back to previous project and check the relationship , lead / lag time and then enter in next project , which is very laborious and time consuming.
So is there a way where i only bring my project till mile stone task and then could copy from previous projects task , relationship , duration and link it to mile stone task in present project.
Eagerly waiting for answers.
Thanks
regards
vinod