I have got the reply to my query by Mr Ismet who is a PP Member.
I have been worrying that the Progress line was showing ahead when it should be in a staright line as the actual % is same as Planned %. but MSP draws the Prgress line to the next working activity by default...
I find this thing a bit strange though..
Cheers,
Member for
22 years 9 months
Member for22 years10 months
Submitted by Alexandre Faul… on Fri, 2012-11-02 15:27
Member for
15 years 9 monthsHello All, I have got the
Hello All,
I have got the reply to my query by Mr Ismet who is a PP Member.
I have been worrying that the Progress line was showing ahead when it should be in a staright line as the actual % is same as Planned %. but MSP draws the Prgress line to the next working activity by default...
I find this thing a bit strange though..
Cheers,
Member for
22 years 9 monthsKumar,this is a "normal"
Kumar,
this is a "normal" behaviour of MS Project; the progress line on summary tasks is supposed to show an average progress status; purely stupid, indeed
Alexandre
Member for
15 years 8 monthsHello Kumar,If you can send
Hello Kumar,
If you can send me your schedule at projectuser(at)fastmail.fm, I'll try to help you.
Regards.
Member for
15 years 9 monthsNeed ur replies guys.......
Need ur replies guys.......