Schedule % Complete

2 replies [Last post]
kumar s
User offline. Last seen 8 years 48 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

Hello All,

Please guide me as i am new to MSP...

1) I have Prepared the schedule and set the baseline and updated the schedule for 1 week.

Now i want to show the Schedule % Complete Column Against the Actual % Complete.But i cannot find the Schedule % Column.Where i can get it.

2) For Showing the Actual % complete which of the % complete can be used as there are 3 types (% complete,Work % complete,Physical % Complete).

3) Is it neccesary to add resources to your project to monitor the Project or it can be done without resource assignment also.

Thanks in advance

Kumar S

Replies

kumar s
User offline. Last seen 8 years 48 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

Hello Sir,

 

thanks for ur reply.

Ok Then is there a way to get the Planned % complete week wise for my project from MSP.

I have to show the week wise planned % of my project to my cleint one week before i start to monitor the project...
In P6 I used to change the data date(Week wise) and get the planned % complete for that week.So is there anything like this which can be done in MSP also.

Paul Harris
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

The % Completes that MSP has are:

  • % Complet which is in actual fact % Duration
  • % Work Complete which may be unlinked from  % Complete
  • Physical % Complete which is a manually entered value.

For any other you will need to enter a formulae ina custom column.

 

Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.eastwoodharris.com

www.primavera.com.au - a Primavera scheduling software resources site