EARLY START AND LATE START S-CURVE

1 reply [Last post]
zuraini lazim
User offline. Last seen 12 years 11 weeks ago. Offline
Joined: 10 Aug 2006
Posts: 8

Hi,

Appreciate if somebody could show me how to fill up the early start and late start date columns as data cannot be entered and on ly show display dates that are similar to START and FINISH dates. I need these info to construct my early start and late start s-curve. I also noted that the milestone task early and late start dates will be the same as start and finish date. How to develop these early and late start dates for a project?

Replies

Izam Zakaria
User offline. Last seen 7 years 45 weeks ago. Offline
Joined: 28 May 2006
Posts: 221

You can't simply fill up the dates, it must came from the logic of activities....you have to establish 1st the project activity and form there the total float will define you the late start and finish....furthermore explanation, reach me at aizam.zakaria@yahoo.com