Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline Milestones

2 replies [Last post]
Philip Kearney
User offline. Last seen 4 years 15 weeks ago. Offline
Joined: 26 Feb 2002
Posts: 19
Groups: None

Hi, Has anyone come up with a way to show baseline milestones in MS PRoject as using MSP 2010 so when I baseline the schedule, tasks are the only one showing the baselines.

 

Tried to do it manually in the Bar Styles option to no avail!

 

Please reply with answer asap as desperate!

Replies

F S
User offline. Last seen 11 years 40 weeks ago. Offline
Joined: 12 Jan 2012
Posts: 3

Hello!,

try this:

in the Gantt Diagram click on the right mouse button and set the "bar styles",( please look to point the mouse in a blank space of the diagram to not focus on only one bar!!!)

Then set a new voice and set these parameters:

name                       Appearence      Show for       start                             end

Milestone Baseline    (custom)      Milestones     Baseline Start (or End)  Baseline Start (or End) (yes it has to be the same beacuse duration is zero)

 

Please beware that if you have saved your baseline in " Baseline" then you must choose"baseline" start (or end), of course if you have chosen Baseline start 1 you have to choose "Baseline start 1".

 

It should works, please tell me if goes.

Regards