Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

constraints in MS project

4 replies [Last post]
G T
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 13 Jan 2011
Posts: 16
Groups: None

Hi can I use two constraints in MS project
I have a task that should finish no later than some date and should start no earlier than some date ... and any time between that period ... I will have to level afterwards and I want MS project to fit this task in this interval....

 

Thanks much

Replies

Tushar khanna
User offline. Last seen 12 years 38 weeks ago. Offline
Joined: 9 Aug 2011
Posts: 12

you cannot apply two constraints to one task.

more info about constraints can be found at Microsoft Project

Hlami Baloyi
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 1 Nov 2011
Posts: 3
Groups: None

G T

 

If you constraint an activity to "finish not later than", you will destroy your critical path, after updating when you reschedule, all activities with a "Finish not later than" constraints will not move their finish dates and hence your critical path will be destroyed.

 

Hope it helps.

Rafael Davila
User offline. Last seen 1 week 1 day ago. Offline
Joined: 1 Mar 2004
Posts: 5240

There are constraints and there are constraints.

A slow moving car on a one way street can slow down all behind him.

Try using a milestone after the activity and set the finish no latter than to this activity while you apply the start no earlier than constraint to the first activity.

Mike Testro
User offline. Last seen 30 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi GT

You should never use constraints in a construction programme - it distorts the logic and criticality.

If you must have a window for any particular task then set up a calendar with non work periods either side of the work window - but do not be surprised at the bizarre results that occur when progressing the predecessors.

And another point - I never let the software do my resource levelling because it will destroy the planned sequences in nanoseconds and you have no idea what it has done to the programme.

Best regards

Mike Testro