Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

constraints

5 replies [Last post]
faisal afsar
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 55
Groups: None
Hi All

these is s bit of problem i am trying to create a schedule which is automatically taking up constraints when i am removing these constraints by making it ASAP the dates are coming back to the day when i am creating the schedule ..................any help guys

Replies

faisal afsar
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 55
Groups: None
thanks steve

got the job done
Steve Macauley
User offline. Last seen 11 years 11 weeks ago. Offline
Joined: 17 Sep 2008
Posts: 6
Groups: None
In MS Project 2003 (it’s probably similar in 2007) there’s an option in Tools->Options->Scheduling called ’New tasks:’, which you can configure to the current date or the project start date. Of course ideally every task in your schedule should be linked to a predecessor.

When constructing a schedule from scratch is it often useful to create a milestone called ’Project Baseline Start’ with an ’Actual Finish’ set to the current date. This can be linked to any tasks that are due to start immediately.

Cheerio...
Steve
Mike Testro
User offline. Last seen 9 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Faisal

Sorry but I have no further suggestions to offer.

Best regards

Mike Testro
faisal afsar
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 55
Groups: None
rather than your sympathy i would honour your suggestion please
Mike Testro
User offline. Last seen 9 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Faisal

I hate Microsoft Project and never use it unless I have to.

You can - I beleive - do a global search and constraint removal.

There is also a default setting somewhere that sets the attributes for new activities - the standard is to put a constraint on every activity - just plain bonkers.

You have my deepest sympathy having to use such rubbish.

Best regards

Mike Testro.