Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

seperate calender in same schedule

No replies
faisal afsar
User offline. Last seen 12 years 27 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 55
Groups: None

hi all

 

have made a schedule which includes both preconstruction and construction phase now i want to assign two seperate calenders one 5 days a week  working to preconstruction stage and the other 6 days a week working calender to the construction phase ...how to go about it   plzzzz help