Trouble Exporting MSProject 2007 files to Primavera Contractor

1 reply [Last post]
Geof K. Baker
User offline. Last seen 13 years 20 weeks ago. Offline
Joined: 5 Jul 2011
Posts: 4
Groups: None

I am having huge problems trying to export a project created in MS Project (by my owner) into Primavera's P4 Contractor.

I need help so that I don't have to recreate the entire project from scratch. Anyone know a way or a file conversion utility to accomplish this?

Replies

William (Bill) Drew
User offline. Last seen 10 years 4 days ago. Offline
Joined: 9 May 2011
Posts: 9
Groups: None

Primavera is not compatible with MSP 2007. You must save your MSP either as MSP 2003 or as an XML file and then import it into P4.