Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project Summary show only one fourth duration of activity

13 replies [Last post]
Kumar Baiju
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Hi Alll

      I have one question about the actual duratin in MS project-2003. I am using 24 hous calander for my prject. when i updated my actual duration E.g. 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. I cannot understand why in summary it comes only nearly one fourth duration

 

4.83 Hrs 2.41 Hrs
20 Hrs 10 Hrs

Replies

Kumar Baiju
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Dear Rafael

         I have seen the Video. That is for Task summry not for the Project summary. I can do also for the task summary but cannot for the project summary. If any other method you have please reply me

Thanks\\

KBJ

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5230
Kumar Baiju
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Dear Rafael

            It is the summary and not editable. please suggest how can i edit it.

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5230

Click where you see None (at Summary Task) and change it to 24 hrs calendar and let me know.

Kumar Baiju
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Dear Rafael

               In my project Calculation mode is automatic and calendar in Task information & project infromatin is same i.e 24 hous.

 

Regards\\

KBJ

238
sample.gif

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5230

Where the calendars different?

If different and you changed the calendar did you run a schedule run?

I use MS Project rarely but because use MS Project 2010 I setup all task mode in automatic.

Kumar Baiju
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Rafael

     It does not solve my problem

KBJ

Kumar Baiju
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Rafael

     It does not solve my problem

KBJ

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5230

Try inserting a column to display Task Calendar, if it differs at a Summary Bar change it to 24 hours and let us know what happened.

Kumar Baiju
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Daer Alexandre

          Thanks for your reply. But i have assign in both fiel 24 hous calendar.

 

Kumar

Kumar Baiju
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Daer Alexandre

          Thanks for your reply. But i have assign in both fiel 24 hous calendar.

 

Kumar