Hi Alll
I have one question about the actual duratin in MS project-2003. I am using 24 hous calander for my prject. when i updated my actual duration E.g. 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. I cannot understand why in summary it comes only nearly one fourth duration
4.83 Hrs | 2.41 Hrs |
20 Hrs | 10 Hrs |