Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual % Complete

4 replies [Last post]
Ahmed KHR
User offline. Last seen 6 years 42 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 65

Dear all,

 

How can I introduce actual % complete to MS Project to get Duration delay?

 

Regards

Replies

Kumar Baiju
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Hi Alll

      I am new for this forum and i ahve no idea how can add any question to this. I have one question about the actual duratin in MS project-2003. i am using 24 hous calander. whan i updated my actual duration Eg 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. i cannot understand why in summary it comes only nearly one fourth duration

4.83 Hrs 2.41 Hrs
20 Hrs 10 Hrs
   
Kumar Baiju
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Hi Alll

      I am new for this forum and i ahve no idea how can add any question to this. I have one question about the actual duratin in MS project-2003. i am using 24 hous calander. whan i updated my actual duration Eg 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. i cannot understand why in summary it comes only nearly one fourth duration

4.83 Hrs 2.41 Hrs
20 Hrs 10 Hrs
   
Trevor Rabey
User offline. Last seen 2 years 6 days ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None

I know what % Complete is. It is just the actual duration divided by the total duration. So if you have a 10 day task and 6 days of actual duration and 4 days of remaining duration, then % Complete = 60%. But I don't know what you mean by "duration delay". What is it?

Darren Kosa
User offline. Last seen 7 years 40 weeks ago. Offline
Joined: 8 Feb 2008
Posts: 256
Groups: None

Hi Ahmed,

This is probably a very simplistic solution, but have you tried experimenting with 'Types' and using fixing work / effort driven when updating actuals?

Regards,

Darren