Activity Progressing!

7 replies [Last post]
Jamie Clarke
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 10

I have updatd an MSP schedule with progress and would like the activity bars to be shaded to indicate the progess. For instance if an activity is 50% complete and I input the data into the "Physical % Complete" comlumn, I would like that activity bar on the gantt chart to be shaded 50% to indicate the progress.

Could you help me please?

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 4 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Trevor,
I did not include status date as it mean to show the progress on bar and also not run the schedule to move all non-started and in progress activities to status date.
Trevor Rabey
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Rodel, in your tracking example, what date is the status date?
Jamie Clarke
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 10
Thanks Rondel, i just needed to adjust my gantt chart wizard. thanks for your help!
Rodel Marasigan
User offline. Last seen 11 weeks 4 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Jaime,
As long as you progress your activity using % complete then even 100% should be doing the same. See sample below
MSP Sample Progress
Jamie Clarke
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 10
Rodel,

Another quick query!

I followed the steps for the progressing and it works fine! but tasks that are at 100% complete, do not have any shading and continue to be displayed the same! can you tell me how i will have the full activity bar shaded completely when at 100%?

Thanks
Jamie Clarke
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 10
Rodel,

Another quick query!

I followed the steps for the progressing and it works fine! but tasks that are at 100% complete, do not have any shading and continue to be displayed the same! can you tell me how i will have the full activity bar shaded completely when at 100%?

Thanks
Rodel Marasigan
User offline. Last seen 11 weeks 4 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Jaime,
Use the % complete to progress your bar instead of Physical %.
Right click then select task information then under General Tab enter Percent Complete or Select Header Column then right click, select insert column then under field name select % complete. Once the % complete column is visible enter your progress.