planed hours

2 replies [Last post]
Dan MÃ¥rtensson
User offline. Last seen 11 years 25 weeks ago. Offline
Joined: 4 Feb 2010
Posts: 59
Hi,

Is there any way to display the planed hours up to status date in msp 2007?

Thanks

// Dan

Replies

Dan MÃ¥rtensson
User offline. Last seen 11 years 25 weeks ago. Offline
Joined: 4 Feb 2010
Posts: 59
Thank you, this works fine!

//Dan
Trevor Rabey
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Yes.
Must have in mind "Planned as of when?".
Say it is as planned as of the day before the project started.
Get the version of the plan that you had on that day.
Set the status date to today.
Use the Tracking Gantt and Tracking Table.
Also, have available the Tracking Toolbar.
Also, format the gridlines to show the status date as a vertical red line on the chart
Select all tasks.
Click the Update as scheduled button om the Tracking Toolbar (2nd from left).
Then see the Actual Work column in the Tracking Table or the Work Table.