Dan Mårtensson
User offline. Last seen 11 years 32 weeks ago. Offline
Joined: 4 Feb 2010
Posts: 59
Hi all planners!

Is there possible to show as in primavera a bar that is critical but also non critical?

Ex:
My first 25% of the activity is ok but the after an update the task has been longer and must show critical.

Hope you understand what I want.

Regards

Dan

Replies

Dan Mårtensson
User offline. Last seen 11 years 32 weeks ago. Offline
Joined: 4 Feb 2010
Posts: 59
Thank you Ismet and Mike!

This helps

//regards Dan
Ismet Kocaman
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 5 Mar 2010
Posts: 26
Thank you Mike. I’m glad to be part of the PP Community.
Mike Testro
User offline. Last seen 33 weeks 10 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Come on Guys

Just a simple answer on one side of the paper will do.

Best regards

Mike Testro

PS Hi Ismet

Welcome to PP - now that you have met up with Rafael it seems that you speak the same language in planning terms - praise be that you express it in English.
Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5240
Or perhaps?

MS Bar Styles

Look at the range of the float bar I defined it not the usual, from ES instead of from EF.

Or maybe?

MS Split
Ismet Kocaman
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 5 Mar 2010
Posts: 26
Mike, I guess that is what you mean ?

Image and video hosting by TinyPic
Mike Testro
User offline. Last seen 33 weeks 10 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Dan

I think you mean you have put some progress on the bar and it is split at the progress line.

In which case only the work still in progress should show critical.

Surely MSP does that automatically.

Best regards

Mike Testro
Dan Mårtensson
User offline. Last seen 11 years 32 weeks ago. Offline
Joined: 4 Feb 2010
Posts: 59
Hello Ismet

I know how to display the critical bars in the gantt chart. But what I seek is the function that Primavera has, the bar can show both blue and red (in this case).

Thanks

Regards

Dan


Ismet Kocaman
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 5 Mar 2010
Posts: 26
Dan,

You can change the current view (I suppose it is the Gantt Chart view that you are currently working on) to display critical task bars in red. e.g. use Tracking Gantt View
on the View menu.

Regards,
Ismet Kocaman